The Alaska SeaLife Center, located in Seward, is the fiscal agent for the North Pacific Research Board. NPRB staff ensures timely reporting and fields requests from grantees. The grants and contracts administrators at the Center handle complex budget issues and track funds.
Yes. All NPRB funds are federal with a CFDA number of 11.472. All federal grant rules apply, including the Fly America Act.
Your agreement with NPRB states: “Reallocation of funds between or among the direct cost categories in the Contractor NPRB Budget Summary Form in Appendix 1 must be approved in writing by NPRB prior to any such reallocated expenditure occurring, if that reallocation exceeds ten percent of the total Contractor budget amount.”
Reallocation of funds between direct cost categories requires permission only if the cumulative amount of budget reallocations is greater than 10% of the total budget amount. If you need to exceed this 10% threshold, you must request approval from NPRB.
Please e-mail requests for budget changes to both the NPRB Science Director and the SeaLife Center. Requests must include:
If an invoice is submitted that shows expenses exceeding the 10% threshold, this invoice will not be paid until a budget change request is approved.
NOAA must approve all foreign travel that occurs on NPRB grants.
Project numbers 700 and higher: Foreign travel specified in your original project budget will be submitted to NOAA automatically for approval upon final approval of your budget. You will receive a release of funds for foreign travel that is separate from the overall release of funds for your project.
Project numbers 699 and lower, or if no foreign travel was originally included in your budget: You must submit a request for foreign travel to NPRB. Note: The NOAA foreign travel approval process can take up to eight weeks, so please make your request as early as possible.
Please e-mail all requests for foreign travel to the NPRB Science Director and the SeaLife Center. Requests must include:
Your agreement with NPRB states: “The NPRB executive director may in his/her sole discretion grant extensions of time in writing if requested at least thirty days before the conclusion of this Agreement.”
NPRB staff consider no-cost extensions on a case-by-case basis, with no guarantee of approval. Please submit requests for a no-cost extensions at least 30 days before the end of the current project period, and send to the NPRB Science Director and the SeaLife Center.
Requests must include:
Due date and review | Semiannual Progress Reports are due beginning with the first July 15 and January 15 after the contract start date, for the first and last six months of the calendar year, respectively, and then every semester thereafter until the contract is completed. If the first report comes due before substantial progress has been made, please just note that in your initial report. Download Progress Report Template
Note: Submitted invoices are not paid until progress reports are received, so timely reporting ensures that funding continues to flow smoothly to your project. If you have questions regarding your project or contract, please contact the NPRB Science Director.
Your agreement with NPRB states: “The Contractor shall submit a final programmatic report within sixty days of the end of the project period indicated in Section 1. NPRB may in its sole discretion choose to treat the final programmatic report as a draft final report, and to submit that draft to peer review. The Contractor will respond timely to all peer review comments, and will revise the draft to a final report in accordance with peer review decisions.”
Your agreement also states: “Ninety percent of all incurred costs authorized and properly reported by the Contractor shall be paid by NPRB within thirty days … The remaining ten percent shall be paid to the Contractor within thirty days following acceptance of the final programmatic report and associated metadata.”
Due date and review | Your final report will be due 60 days after the ending date of your agreement. Please refer to the Final Report Format and Review Criteria document for further guidance.
Final reports are read thoroughly, and revisions are frequently required. Your report will be compared against your original proposal, so you must specifically address why any objectives were not met.
Final release of funds | The final 10% of the total budget will be released upon approval of your final report and successful transfer of metadata and data to the NPRB. If revisions are required, this amount will be held until your revisions satisfy the reviewer(s).
Your agreement with NPRB states: “The Contractor shall publish and make its results available to the public and other researchers as requested by NPRB. The Contractor agrees to report its data to an agreed-upon system, in accordance with specifications in a data management and information transfer plan, which will be developed by NPRB, in consultation with the Contractor.” Learn more